FY2005 Plans involving Web/Print
October 15, 2004
Notes
This document contains a listing of OPO projects that affect Web/Print. What
each project actually is is not specified here. This document simply is a "back-of-the-envelope"
estimate on work load, time, and priority of the projects.
The projects are listed with their respective groups in order of priority
and date of work/completion. Each project is a table listing its basic characteristics.
These characteristics are:
- Table border color indicates priority. Priorities are those determined
by the group leads.
The only "real" priority is whether the project is in the "Goddard Plan"
or not. If it is in the Plan, then the HST Project overseers will require
that it be so done as it is stated. Otherwise, the priorities are relative:
Everyone wants everything done, but if something must fall, then this is
how they should fall.
-
Red border: High priority
Must really be done. If the project is
in the Goddard Plan, it is noted. Projects with hard deadlines will also
be classified High.
Blue border: Medium priority
In general, try to get it done, but its
not in the Plan and there are no particular time constraints.
Gray border: Low priority
Wish-list item: If it can be fit, that would be great.
- First row: Project title
- Row "Group": The group who owns this project.
- Row "Priority/Date": The priority is stated (as explained above). Also,
if known, the projected quarter(s) work will occur and/or hard deadlines
which constrain the project.
- Row "State": The state of the product. This is an attempt to characterize how much is known about the product. Possible states are:
- "new": A brand new product that has had no conceptualization done. This project will need to start from ground zero.
- "conceptualized": The concept has been well defined. Needs content to be developed.
- "content generated": Content has been generated.
- "designed": The product has been designed. Simply needs to be made.
- "mature/add-on": The product is part of a series that has already been built. This one is simply another in the series.
- Row "Size": The critical element which characterizes the time/workload
the project will require. Possible statements are:
- Fix-By-Friday: Expected to take less than a week with minimal web/print
involvement.
- small: Up to 2 weeks worth of effort.
- medium: Up to 7 weeks worth of effort.
- large: Up to 13 weeks worth of effort.
- x-large: Requires more than a quarter of effort.
- Qualifier "Scheduled as an Update": This project will be scheduled
with other projects similarly marked as "updates".
- Qualifier 50%: generally used to indicate that the project will not
require resources for more than 20 hours a week. Example: a project may
take 5 weeks to complete, but because of downtime waiting for external
participants, will only take 50% time during those 5 weeks.
- Row "Resources": Expected roles that will be required by the project. Specific
terms include:
- Whole team: Project will require a whole production team, including
production manager, customer representatives, etc.
- List of the individual roles
- Row "Notes": Any other information relevant to the project.
Online Outreach
| JWST Update |
| Group |
Online Outreach |
| Priority/Date |
High (Goddard Plan)/Q3 |
| State |
mature/add-on |
| Size |
medium |
| Resources |
writer, designer, programmer |
| Notes |
|
| Hubblesite Long Range Plan/Design |
| Group |
Online Outreach |
| Priority/Date |
High (Goddard Plan) |
| State |
new |
| Size |
medium |
| Resources |
whole team |
| Notes |
|
| Big new image gallery |
| Group |
Online Outreach |
| Priority/Date |
High (Goddard Plan) |
| State |
new |
| Size |
large |
| Resources |
whole team |
| Notes |
In conjunction/after long range plan. |
| Viewspace: Skylines (12) |
| Group |
Online Outreach |
| Priority/Date |
High (Goddard Plan) |
| State |
conceptualized |
| Size |
medium |
| Resources |
designer, programmer |
| Notes |
Collaboration with Informal Science. |
| Clean attic: Hubblesite future planning. |
| Group |
Online Outreach |
| Priority/Date |
High |
| State |
new |
| Size |
medium |
| Resources |
whole team |
| Notes |
|
| HST 15th Anniversary. |
| Group |
Online Outreach |
| Priority/Date |
High/Apr05 |
| State |
new |
| Size |
medium |
| Resources |
whole team |
| Notes |
Completely unknow what this will entail. High level decisions should be made by end of Oct04. |
| Viewspace: Image tours |
| Group |
Online Outreach |
| Priority/Date |
Medium |
| State |
new |
| Size |
medium |
| Resources |
team |
| Notes |
Collaboration with Informal & Formal Ed. |
| Viewspace: Misconceptions |
| Group |
Online Outreach |
| Priority/Date |
Low |
| State |
new |
| Size |
medium |
| Resources |
team |
| Notes |
Collaboration with Formal/Informal. Will begin after a critical mass (10 or more) have been developed. |
| Bulletin board- web chats |
| Group |
Online Outreach |
| Priority/Date |
Low |
| State |
conceptualized |
| Size |
medium |
| Resources |
whole team |
| Notes |
When an opportunity arises, this will be setup. |
| Hubblesite: Generate awareness |
| Group |
Online Outreach |
| Priority/Date |
Low |
| Size |
small |
| Resources |
writer |
| Notes |
Collaborate with Informal Science, News. |
Formal Education
| Hubble Classroom (4) |
| Group |
Formal Ed. |
| Priority/Date |
High (Goddard Plan) / Q1, Q2, Q3, Q4 |
| State |
mature/add-on |
| Size |
small: schedule as an Update |
| Resources |
writer, designer |
| Notes |
1 per quarter: Can be any of Fast Fact, GO, Tales, Myths. |
| Solar System Trading Cards: K-2 version |
| Group |
Formal Ed. |
| Priority/Date |
High (Goddard Plan) |
| State |
design prototype |
| Size |
small |
| Resources |
writer, designer |
| Notes |
Prototype testing done. Ready for production |
| Kids News - New news |
| Group |
Formal Ed. |
| Priority/Date |
High (Goddard Plan) / Q2, Q4 |
| State |
mature/add-on |
| Size |
small: Schedule as an Update |
| Resources |
writer, designer |
| Notes |
2 per year. A formal process needs to be developed. |
| Galileo to Hubble: Discoveries |
| Group |
Formal Ed. |
| Priority/Date |
High |
| State |
New |
| Size |
large |
| Resources |
whole team |
| Notes |
Add-on to activity, but individual concept has not been defined. |
| HDF Academy Redesign |
| Group |
Formal Ed. |
| Priority/Date |
High (Goddard Plan) |
| State |
new |
| Size |
large |
| Resources |
Team |
| Notes |
|
| Galileo to Hubble Redesign |
| Group |
Formal Ed. |
| Priority/Date |
High (Goddard Plan) |
| State |
conceptualized |
| Size |
large |
| Resources |
whole team |
| Notes |
In design phase. |
| New Lithographs (2) |
| Group |
Formal Ed. |
| Priority/Date |
High (Goddard Plan) |
| State |
mature/add-on |
| Size |
fix-by-friday: Schedule as an Update |
| Resources |
writer, designer |
| Notes |
2 per year. |
| Web site section: Colleagues & Scientists |
| Group |
Formal Ed. |
| Priority/Date |
High (Goddard Plan) |
| State |
Conceptualized |
| Size |
medium |
| Resources |
team |
| Notes |
Basically adding text content to this section. |
| Web site section: Careers |
| Group |
Formal Ed. |
| Priority/Date |
High (Goddard Plan) |
| State |
New |
| Size |
medium |
| Resources |
team |
| Notes |
Basically adding text content to this section. |
| Evaluation Survey Support |
| Group |
Formal Ed. |
| Priority/Date |
Medium |
| State |
new |
| Size |
small |
| Resources |
writer, designer, programmer |
| Notes |
News, Informal Science, update Amazing Space surveys. |
| Teacher page consistency |
| Group |
Formal Ed. |
| Priority/Date |
Medium |
| State |
new |
| Size |
Fix-By-Friday: schedule as an Update |
| Resources |
team |
| Notes |
|
| E/PO: Lessons Learned + Monographs |
| Group |
Formal Ed. |
| Priority/Date |
Low |
| State |
new |
| Size |
small: schedule as an Update |
| Resources |
writer, designer |
| Notes |
|
| HUDF Poster |
| Group |
Formal Ed. |
| Priority/Date |
Low |
| State |
new |
| Size |
Medium |
| Resources |
designer, writer |
| Notes |
|
| Web site section: Clip art |
| Group |
Formal Ed. |
| Priority/Date |
Medium |
| State |
new |
| Size |
medium |
| Resources |
whole team |
| Notes |
|
| HST Model activity sheet |
| Group |
Formal Ed. |
| Priority/Date |
Low |
| State |
new |
| Size |
small: schedule as an Update |
| Resources |
writer, designer |
| Notes |
Move from old edu.space area. |
| Hubble Primer Update |
| Group |
Formal Ed. |
| Priority/Date |
Low |
| State |
new |
| Size |
medium |
| Resources |
writer, designer |
| Notes |
Is this also a print product? |
Informal Science
| Scala server conversion, commision, & shake-out |
| Group |
Informal Ed. |
| Priority/Date |
High |
| State |
design |
| Size |
small |
| Resources |
programmer |
| Notes |
Build is in progress. |
| Scala server/player maintenance |
| Group |
Informal Ed. |
| Priority/Date |
High |
| State |
new |
| Size |
medium/continual |
| Resources |
programmer |
| Notes |
|
| Scala server/player: Remote system admin rollout |
| Group |
Informal Ed. |
| Priority/Date |
medium |
| State |
new |
| Size |
medium |
| Resources |
programmer |
| Notes |
|
| PReSS image gallery sorted by size. |
| Group |
Informal Ed. |
| Priority/Date |
Medium |
| State |
new |
| Size |
medium |
| Resources |
team |
| Notes |
|
| HubbleSOURCE expansion |
| Group |
Informal Ed. |
| Priority/Date |
Medium |
| State |
new |
| Size |
small |
| Resources |
designer (<20%), programmer (<20%) |
| Notes |
Basically to support author-added content to the site. |
Origins
| SSERD Data Consistency Project |
| Group |
Origins |
| Priority/Date |
Medium |
| State |
new |
| Size |
medium |
| Resources |
Technical Facilitator,Design Facilitator |
| Notes |
Assist in plan to better formalize data input and data consistency processes. |
| SSERD 508 Compliance |
| Group |
Origins |
| Priority/Date |
Medium |
| State |
new |
| Size |
medium |
| Resources |
Programmer, designer (20%) |
| Notes |
Rework site structure to be 508 compliant. Designer needed to help in any graphics modifications. |
| SSERD Statistics/Usage analysis |
| Group |
Origins |
| Priority/Date |
Medium |
| State |
new |
| Size |
medium |
| Resources |
Programmer, designer (20%) |
| Notes |
Rework site structure to be 508 compliant. Designer needed to help in any graphics modifications. |
| ORIGINS website redesign: Phase II |
| Group |
Origins |
| Priority/Date |
Medium |
| State |
new |
| Size |
medium |
| Resources |
Team |
| Notes |
This phase redesigns the missions/NASA side of the Origins site. |
News
| General newscenter updates |
| Group |
News |
| Priority/Date |
High (Goddard Plan) |
| State |
new |
| Size |
medium |
| Resources |
writer, designer, programmer |
| Notes |
Definitely schedule one, allowing for a second later in
the year. |
Web/Print
| Graphic and Project archive server |
| Group |
Web/Print |
| Priority/Date |
High |
| Size |
medium |
| Resources |
Designer, programmer |
| Notes |
|
| Infrastructure: Server maintenance (3) |
| Group |
Web/Print |
| Priority/Date |
High |
| Size |
small: 3 one-week periods. |
| Resources |
programmer |
| Notes |
|
| Infrastructure: Testbed maintenance (2) |
| Group |
Web/Print |
| Priority/Date |
High |
| Size |
small: 2 one-week periods. |
| Resources |
programmer |
| Notes |
|
| Infrastructure: Hardware/software Budget Planning |
| Group |
Web/Print |
| Priority/Date |
High |
| Size |
small: One-week |
| Resources |
programmer |
| Notes |
|